Howe is small enough to run a single inspection day. The request has to be in by three in the afternoon on Tuesday to be inspected on Wednesday. Miss that window and the next slot is the following Wednesday, so a missed phone call costs a week rather than a day.
That one fact changes how a house gets sequenced here. Work has to be genuinely ready before Tuesday afternoon, not merely finished sometime that week, and a trade running a day late pushes everything behind it a full seven days.
The permit itself expires 180 days from issue unless construction has started and passed an inspection. The city can grant a short extension on a written request, but the clock is real and it does not care why.
Before the certificate of occupancy the city looks for house numbers at least four inches tall and visible from the road, meter boxes at grade with the nuts visible, cleanouts at grade and clear of concrete, and the grass and sidewalk in order. None of it is hard. All of it delays a closing if it is left to the last week.